Claims examples
Displaying results 1 to 8 out of 8
- 1
12/06/2013 -
A subsea engineering company was contracted by an oil major to design a series of subsea flowlines, carrying oil and gas products from the wellhead to the riser foot. The design factored in an intended life-span of 15 years....
12/06/2013 -
A major survey company was contracted to survey the seabed for the routing of a power cable. This cable was used to connect to an offshore wind farm to the power grid via a substation ashore. Unfortunately, the routing was not...
12/06/2013 -
A surveyor was contracted to carry out a debris clearance survey, including a bathymetric sounding. This report was carried out and issued, but unfortunately, the depths on the report were not correct. The site was actually...
12/06/2013 -
A consultant was engaged to notify all interested parties along a route of a new telecommunications cable. The consultant did this in accordance with its principal’s instructions. However, whilst laying the cable, the ship...
12/06/2013 -
A consultant was contracted to carry out a spudcan penetration analysis of the seabed prior to a mobile jack-up drill putting its legs down. The analysis was not carried out effectively. The consultant advised that the rig was...
17/05/2013 -
A consultant was engaged to notify all interested parties along a route of a new telecommunications cable. The consultant did this in accordance with its principal’s instructions. However, whilst laying the cable, the...
17/05/2013 -
A surveyor was contracted to carry out a debris clearance survey, including a bathymetric sounding. This report was carried out and issued, but unfortunately, the depths on the report were not correct. The site was actually...
08/03/2012 -
The Swedish Hydrographic Office produced a navigation chart with an incorrectly marked rock. A Russian tanker struck the rock and filed a claim against the organisation. The Swedish Supreme Court held that the Hydrographic Office...